Minutes of Facilities
Committee Meeting
2007/11/12
Attendees: Tracey Hamilton, Ruth Milner, Jim
Shepherd, Delilah Walsh, Don
Weinkauf, Karin Williams, Russell Wrenn
Absent: Cecilia McCord, Pete Whiteis
Scribe: Ruth Milner
- Old Business
- Overhead
utility lines: Delilah Walsh – Socorro
Electric has moved the power lines to a new pole across the street from
CVCS. Phone and cable companies were contacted but have elected not to
change anything at this time. (Not required.) Item complete.
- Soil
compaction
test: Russell Wrenn – No update from the NMT
professor who offered to advise; however Kent recommended having 5
bores done: one for each classroom pod and two for E Pod. These should
be done soon so the pod locations can be finalized.
- CVCS in
SCS District facilities plan:
Karin Williams – No updates on the district plan; Karin will check with
Cheryl Wilson re progress on this.
- E Pod
Legislative committee meetings: Karin Williams – Karin
learned recently from
Sharon Ball that the meeting CVCS needs to be part of will not be held
until March. Some other things need to be done to prepare for that
meeting. She will work with Sharon and keep tabs on this.
- Project
Manager: Jim Shepherd – Some modifications have
been made to the
text of the RFP, but we will hold off on issuing it until we know
whether
the builder will include this service in the contract.
- E Pod
drawings: Kent Beierle – These have been given lower
priority than getting the modulars underway.
- New Business
- Review B
Pod classroom design: Jim displayed a Sketchup file
showing the latest design for the K-3 classroom pod while we talked
with Kent on a conference phone. No written specifications
were presented at the meeting. Committee members liked the layout of
staggered rectangles with different earth-toned exterior colors and a
courtyard in the center. Classrooms for 1st through 3rd grades are 26'
square; kindergarten is slightly larger. Each classroom has a door off
the courtyard and an additional door to the outside, where a small
patio or garden area could be located for class use. The design shows a
translucent PV array that doubles as a shade structure over the open
courtyard; this was visually appealing as well as functional. B Pod
comprises 5 "modules" (4 classrooms and a shared bathroom/utility area)
which
would be constructed in a total of 9 pieces. Members had a few
questions/comments:
- Roofs:
Pros and cons of pitched roofs vs the
flat roofs shown. Flat roofs are easier to build and are
more conducive to adding "green" features. They also would not cause
height
problems for transportation of the modules, whereas a pitched roof
would probably have to be framed separately and/or added on-site. Kent
noted that the flat roofs would use white thermoplastic
polyolefin (TPO) membranes. There was some
discussion of "green" roofs beyond insulation, e.g. rooftop gardens.
Doing something like this would require the roof to be stronger. The
committee suggested that the roofs be built so they could support this
type of use to keep our future options open, and also to build in a few
ducts to allow the installation of solar heating panels. It would also
need to allow rainwater to run off and be collected.
- Passive
heating/cooling: The design shows trombe walls near each
classroom. Kent explained that these would be connected through
underground ducting to the crawlspace beneath the classrooms, and that
a small fan in each one would ensure movement of warm air. A couple of
committee members expressed skepticism about the effectiveness of
trombe walls. Members did like the vine-covered screens shown to the
west of classroom windows, which would be inexpensive and pleasant to
look at.
- Lighting:
Is the natural lighting available through the windows adequate to avoid
turning lights on most of the time? Kent pointed out that although the
windows do not look large in the overall design, the scale is such that
most are actually 5' high and 10' long, and should provide plenty of
light. His goal is for lights to never be needed during the daytime.
- Built-ins:
It was pointed out that the final design should include some built-ins
or other equipment, to cover more things with the lease. However we also
want to allow some flexibility for the teachers to arrange their rooms.
- Courtyard:
Would noise from the courtyard be disruptive to other classes if one
class was working there? Kent thinks not because the surfaces would
most likely be stucco, which should absorb sound fairly well. There was
some discussion about how to make use of the courtyard space, for example,
for hanging coats (though it would need to be covered properly). Also,
built-in tables and benches may not be the best way to go, especially
if funds and time are an issue initially. A couple of picnic tables
with a gravel surface could do the job and would be more flexible, at
least until the teachers have some experience making use of the space.
Overall the committee liked the basic design and recommended that, pending Governing Council approval, Kent could move
ahead with getting quotes from the manufacturers.
SUMMARY
OF ACTION ITEMS:
- Present B Pod design to Governing Council at Nov 14 meeting, with recommendation to proceed (Jim Shepherd)
- Cost and information for compaction testing
before the next scheduled facilities meeting (Russell Wrenn)
- Update
CVCS site plan in the District's plan and keep a look
out
for the Interim Committee Request for the PSCOC Meeting in March
(Karin Williams)